21 hari → 36 jam
Shipping lead time
99,7%
Compressor uptime
5 dokumen
Compliance docs
MTC + Heat No.
Traceability
Onshore gas operator Cepu with 99.5% uptime SLA — compressor inlet valve failed over weekend, PIM mobilized spare from Singapore via air freight, on-site 36 hours from RFQ confirmation. Pertamina EP audit passed.
Compressor station inlet valve failed unexpectedly on Friday night. OEM replacement lead-time 21 days ex-factory. 99.5% uptime SLA at risk — material contract penalty if not resumed within 72 hours.
PIM located spare via independent distributor network in Singapore. Air freight Changi → Jakarta → Cepu with pre-cleared customs. MTC + Inspection Report + Heat Number traceability documents attached per Pertamina EP audit requirements.
The pre-cleared air-freight route successfully delivered the spare part on-site within 36 hours from RFQ confirmation. The compressor resumed operation on Monday morning with complete MTC + traceability docs, holding the uptime SLA at 99.7%.