Over-stock = capital sleeping in the warehouse. Under-stock = units idle waiting for parts. The key is not stocking more, but stocking the right parts based on risk and production impact.
Reorder point = (average daily usage × lead-time days) + safety stock. For remote sites with long lead times, safety stock must reflect variability — not an optimistic average. Vital parts at remote sites need a thicker buffer than those near a city warehouse.
Lean internal stock is only safe when backed by a fast-responding supplier. That is why PIM targets < 24-hour quote response and maintains a sourcing path for Vital parts — letting you shift part of your "safety stock" onto supplier capacity rather than your own shelves. For larger fleets, we can build the critical-parts list together with your maintenance team.